What has been done?

Contracting with the Nyborg company to set up a turnkey factory.

Purchase of the laser device and 80% of the equipment arriving in Izmir.

Buying land in Izmir by installments system, paying more than a third of the amount, settling it and providing it with all services.

Backfilling and strengthening the factory floor in the amount of one hundred and forty thousand dollars.

Competition for land in Mersin with an area of ​​200 acres.

The concession was taken for a plot of land in Sirte, with an area of ​​100 acres.

Completion of concrete construction.

Extracting all papers, government approvals and environment report.

Securing 80% of the project budget.

Factory Operation Plan

METHODOLOGY

Membrane cell production, diaphragm cell and mercury cell production is the most advantageous compared to the production is much more efficient.

The membrane cell process requires less energy and is much more environmentally friendly than it produces hazardous waste products such as mercury or asbestos. In addition, working with process is extremely safe. It is possible to produce caustic soda continuously with high quality with low maintenance costs. Yearly on-stream working hours will be 8000 hours.

Photos from the Factory

What has been done? Lineer Kostik What has been done? LİNEER KOSTİK SODA INDUSTRY JOINT STOCK COMPANY,Lineer, Kostik, Contracting, Nyborg, turnkey factory, laser device, equipment, land in Izmir, installments, Backfilling, strengthening, factory, floor. Competition, Mersin, concession, plot of land, Siirt, Completion ,concrete, construction, papers, government, approvals, environment report, project budget LİNEER KOSTİK SODA INDUSTRY JOINT STOCK COMPANY Lineer Kostik, Contracting with the Nyborg company to set up a turnkey factory. Purchase of the laser device and 80% of the equipment arriving in Izmir. Buying land in Izmir by installments system, Backfilling and strengthening the factory floor. Competition for land in Mersin.The concession was taken for a plot of land in Siirt. Completion of concrete construction. Extracting all papers, government approvals and environment report. Securing 80% of the project budget